The Board of Directors has decided to change contractors for the remaining phases of the balcony project. Anchored Construction will complete phase 3 this year and is scheduled to...
ADCO South has started to tear off building #19 and they anticipate completing this building by Friday, July 19th or sooner. There has been an increase of plywood replacement...
Dear Quail Creek Homeowners, Unfortunately, the Annual Meeting has been canceled due to No Quorum. The Adjourned Annual Meeting date has been scheduled for Wednesday, June 19th at 5pm...
The Board of Directors is pleased to announce that the association has finally been approved by the city to commence the balcony repair project and they have accepted the...
Dear Quail Creek Residents! B2R Consulting has completed the construction design details needed to start the balcony repair project. The next step is for those details to be filed...
The City of Laguna Hills is requiring the detector/carbon monoxide form to be signed by every homeowner to receive a final roofing city permit for your building for the...
Dear Quail Creek Residents, ADCO South has completed building #1, #2, #3, #4, and #5 of roof replacement project. They will be starting building #6 on Monday, September 25,...
The Board of Directors is pleased to announce the construction of additional hand rails to the new bridge and restoring the direct walkway with steps. This construction will begin...
Dear Homeowners/Residents:This letter is being provided to you on behalf of the Board of Directors (“Board”) of Quail Creek-La Paz Condominium Association (“Association”) to update you on the need...
With a sad heart, Demerie Edington will be leaving Action Property Management as of April 22nd. We want to thank her for her time with Quail Creek & Action. Effective...