Roofing and Balcony Project Updates

Posted By on July 26, 2024

ADCO South has started to tear off building #19 and they anticipate completing this building by Friday, July 19th or sooner. There has been an increase of plywood replacement specifically for building #19. Building #20 is scheduled for tear off on Monday, July 22nd.

RAYCO Exteriors has completed the balcony repairs for phase #1 except for unit #2 that requires engineering plans/drawings. Currently phase #2 is 50 percent completed, they are working on units #86 and #94. On the week of July 15th, RAYCO will begin working on units #101 and #102. The balcony project is still scheduled to be completed within the 9-month timeline.